Question # 1
The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the
agreement of the team.
Which Agile principle MOST influences this course of action? | A. Deliver on time. | B. Never compromise quality. | C. Build incrementally from firm foundations. | D. Develop iteratively. |
A. Deliver on time.
Question # 2
What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B? | A. The Project Manager should extend the timescale of Timebox B and shorten Timebox C. | B. The Solution Development Team should change a Must Have requirement into a Should Have in the Prioritised Requirements List. | C. The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities. | D. The Project Manager should move a Must Have requirement from Timebox B into Timebox C. |
C. The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.
Explanation:
C. The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.
Rationale:
In Agile Project Management, priorities are often reassessed and reprioritized based on new information or changes in the project's context. The need for a secondary exit due to compliance with fire safety regulations would necessitate such a reassessment. The Business Visionary and Business Sponsor, who provide the vision and funding for the project, together with the Solution Development Team, who are responsible for implementing solutions, should collaboratively review the Prioritised Requirements List to reflect this new priority. This change must be agreed upon by these key stakeholders to ensure that it aligns with the business needs and project goals.
Question # 3
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project
Management when developing the Feasibility Assessment? | A. The new Project Manager should NOT be involved in finalising the
Feasibility Assessment. | B. The Architecture Angels' Finance Director should approve the final
Business Case as part of the Feasibility Assessment. | C. The Earth Excavations' Head Gardener should contribute to the outline
solutions considered for the gardens. | D. The different options should be presented to the 'Hoy for Hoy Hall' Action
Group for their feedback before the chosen outline solution is finalised. | E. The Timber Tigers' Site Manager should be the sole approver of the
finalised Feasibility Assessment before development commences. |
B. The Architecture Angels' Finance Director should approve the final
Business Case as part of the Feasibility Assessment. D. The different options should be presented to the 'Hoy for Hoy Hall' Action
Group for their feedback before the chosen outline solution is finalised.
In Agile Project Management, it's important to involve key stakeholders and to ensure that there's a collaborative approach to project decisions. Considering the Agile principles and the given scenario, the appropriate application of Agile to the Feasibility Assessment would likely involve the following statements:
B. The Architecture Angels' Finance Director should approve the final Business Case as part of the Feasibility Assessment. In Agile, it's crucial to ensure that the business aspect of any project aligns with the financial feasibility. The Finance Director's approval would be significant in validating the economic viability of the project.
D. The different options should be presented to the 'Hoy for Hoy Hall' Action Group for their feedback before the chosen outline solution is finalised. Agile encourages stakeholder engagement and iterative feedback. Presenting options to the action group aligns with the Agile value of customer collaboration over contract negotiation, allowing for community input that could be vital due to the building's heritage status and the community's interest.
Question # 4
The Web Content Manager has provided the Web Developer with a mock up
of the 'Contact Us' page, to be created for the new coffee bar insurance
product. When producing the code, the Web Developer has created a button
that reads 'Delete' instead of 'Cancel'.
What action should the Web Content Manager take? | A. Prepare a defence for when the problem is identified, ensuring the
responsibility is with the Web Developer. | B. Hide the problem and hope that this detail can be changed at a later date. | C. Raise an issue to the Project Manager when the solution is deployed. | D. Discuss the issue with the Web Developer and decide what action is
required to change this detail. |
D. Discuss the issue with the Web Developer and decide what action is
required to change this detail.
Explanation:
The most constructive and collaborative action the Web Content Manager should take is:
D. Discuss the issue with the Web Developer and decide what action is required to change this detail.
Direct communication and collaboration between the Web Content Manager and the Web Developer are essential in Agile environments to promptly address misunderstandings or mistakes. Discussing the issue openly allows for a quick resolution and ensures that the final product aligns with the project's requirements. This approach fosters a positive working relationship, encourages shared responsibility for the project's success, and avoids unnecessary delays or conflicts.
Question # 5
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.
Is this an appropriate action related to acceptance criteria? | A. Yes, because only Must Have requirements should be fully understood. | B. Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox. | C. No, because it is necessary to understand the full detail of all the work for completion in the Solution Development Timebox during Investigation. | D. No, because it indicates that the Solution Development Team has NO intention of delivering the Should Have requirements. |
B. Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.
Explanation:
B. Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.
Rationale:
In Agile Project Management, flexibility is key. It is important to prioritize work based on the value it provides and the necessity of the requirement. "Should Have" requirements are important but not critical, and they can be subject to change as the project progresses and as more information becomes available. Deferring the detailed setting of acceptance criteria for a "Should Have" requirement that might be dropped is a practical approach to managing workload and focusing efforts on the most critical aspects of the project first. This approach is in line with Agile's principle of responding to change over following a fixed plan.
Question # 6
The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are
four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and
to know who should be where. Some of the contractors have started to turn up late to the site.
Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The
Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.
Answer the following questions about motivating the contractor teams according to Agile Project Management.
How should the Project Manager encourage the resources to operate more successfully? | A. Facilitate a workshop with the Solution Development Team to establish a co-ordinated Timebox Plan. | B. Hold a separate Daily Stand-up meeting for contractors only. | C. Provide a detailed plan of activity for each contractor team. | D. Schedule the electrical and plumbing teams so that they work on different Timeboxes. |
A. Facilitate a workshop with the Solution Development Team to establish a co-ordinated Timebox Plan.
Question # 7
Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate Solution Developer? | A. Accustomed to bringing in contract staff for short periods of time. | B. Closely manages the building team so that they consistently produce high-quality work. | C. Is able to represent the team in all daily meetings. | D. An experienced builder who is good at turning a brief into a practical design. | E. Is empowered by Timber Tigers' management to make decisions on the building work. |
B. Closely manages the building team so that they consistently produce high-quality work. D. An experienced builder who is good at turning a brief into a practical design.
APMG-International AgilePM-Practitioner Exam Dumps
5 out of 5
Pass Your Agile Project Management (AgilePM) Practitioner Exam Exam in First Attempt With AgilePM-Practitioner Exam Dumps. Real AgilePM Exam Questions As in Actual Exam!
— 78 Questions With Valid Answers
— Updation Date : 22-Nov-2024
— Free AgilePM-Practitioner Updates for 90 Days
— 98% Agile Project Management (AgilePM) Practitioner Exam Exam Passing Rate
PDF Only Price 99.99$
19.99$
Buy PDF
Speciality
Additional Information
Testimonials
Related Exams
- Number 1 APMG-International AgilePM study material online
- Regular AgilePM-Practitioner dumps updates for free.
- Agile Project Management (AgilePM) Practitioner Exam Practice exam questions with their answers and explaination.
- Our commitment to your success continues through your exam with 24/7 support.
- Free AgilePM-Practitioner exam dumps updates for 90 days
- 97% more cost effective than traditional training
- Agile Project Management (AgilePM) Practitioner Exam Practice test to boost your knowledge
- 100% correct AgilePM questions answers compiled by senior IT professionals
APMG-International AgilePM-Practitioner Braindumps
Realbraindumps.com is providing AgilePM AgilePM-Practitioner braindumps which are accurate and of high-quality verified by the team of experts. The APMG-International AgilePM-Practitioner dumps are comprised of Agile Project Management (AgilePM) Practitioner Exam questions answers available in printable PDF files and online practice test formats. Our best recommended and an economical package is AgilePM PDF file + test engine discount package along with 3 months free updates of AgilePM-Practitioner exam questions. We have compiled AgilePM exam dumps question answers pdf file for you so that you can easily prepare for your exam. Our APMG-International braindumps will help you in exam. Obtaining valuable professional APMG-International AgilePM certifications with AgilePM-Practitioner exam questions answers will always be beneficial to IT professionals by enhancing their knowledge and boosting their career.
Yes, really its not as tougher as before. Websites like Realbraindumps.com are playing a significant role to make this possible in this competitive world to pass exams with help of AgilePM AgilePM-Practitioner dumps questions. We are here to encourage your ambition and helping you in all possible ways. Our excellent and incomparable APMG-International Agile Project Management (AgilePM) Practitioner Exam exam questions answers study material will help you to get through your certification AgilePM-Practitioner exam braindumps in the first attempt.
Pass Exam With APMG-International AgilePM Dumps. We at Realbraindumps are committed to provide you Agile Project Management (AgilePM) Practitioner Exam braindumps questions answers online. We recommend you to prepare from our study material and boost your knowledge. You can also get discount on our APMG-International AgilePM-Practitioner dumps. Just talk with our support representatives and ask for special discount on AgilePM exam braindumps. We have latest AgilePM-Practitioner exam dumps having all APMG-International Agile Project Management (AgilePM) Practitioner Exam dumps questions written to the highest standards of technical accuracy and can be instantly downloaded and accessed by the candidates when once purchased. Practicing Online AgilePM AgilePM-Practitioner braindumps will help you to get wholly prepared and familiar with the real exam condition. Free AgilePM exam braindumps demos are available for your satisfaction before purchase order.
Send us mail if you want to check APMG-International AgilePM-Practitioner Agile Project Management (AgilePM) Practitioner Exam DEMO before your purchase and our support team will send you in email.
If you don't find your dumps here then you can request what you need and we shall provide it to you.
Bulk Packages
$60
- Get 3 Exams PDF
- Get $33 Discount
- Mention Exam Codes in Payment Description.
Buy 3 Exams PDF
$90
- Get 5 Exams PDF
- Get $65 Discount
- Mention Exam Codes in Payment Description.
Buy 5 Exams PDF
$110
- Get 5 Exams PDF + Test Engine
- Get $105 Discount
- Mention Exam Codes in Payment Description.
Buy 5 Exams PDF + Engine
Jessica Doe
AgilePM
We are providing APMG-International AgilePM-Practitioner Braindumps with practice exam question answers. These will help you to prepare your Agile Project Management (AgilePM) Practitioner Exam exam. Buy AgilePM AgilePM-Practitioner dumps and boost your knowledge.
|